Monday, February 25, 2008

Doors Installed

Its been two weeks since the last post so I wanted to give everyone an update. The sheet rocking is complete and some of the finishing work is now being completed in the new room and basement. Two doors were installed in the basement (one leading to the bilco doors and one leading to the old part of the basement which we plan to use for storage). The hardware on the french doors leading into the new room has also been installed.

The trim is partially completed in the basement and all the electric and lighting is now installed in both the new room and the basement. Since none of these updates make for particularly exciting pictures - there are no pictures with this post.

Later this week the demolition of the kitchen is expected to start and next weekend they will begin to install the new heating and air conditioning unit in the attic. This new unit will serve the upstairs of the house and the existing unit will serve the downstairs (including the new room and basement).